Horizontal
×

Tourism Australia · Client Dashboard

Please enter the access password to view the project dashboard.

For access support, contact your Horizontal Project Manager.
Horizontal
×
Client Dashboard · May 2026 — Feb 2027

AEM → Sitecore AI Migration

On Track Last refresh Mon 8 Jun 2026
This dashboard is refreshed every Monday with the latest project status. We have set this up not to replace monday.com or Confluence but as a hub for you to find information easily.
You are here
M1
May 2026
M2
Foundation
Jul 2026
M3
Build & Migrate
Nov 2026
M4
Go Live
Jan 2027
M5
Hypercare
Feb 2027
June 2026
Session In person Milestone Holiday
Mon
Tue
Wed
Thu
Fri
1
Pre-checklist deadlineComplete by today
2
TA onboarding to HDSyd afternoon
✈ George arrives Syd
3
KickoffSyd 4–5pm
4
Tech onboardingSyd 3–4pm
5
Business Overview1 hr
8
TA Public Holiday
9
Content, DAM & MultilingualSyd 3–4:30pm
10
Technical ImmersionSyd 3–5pm
Transperfect call1:30pm Syd
11
Content ImmersionSyd 3–5pm
12
Design ImmersionSyd 1:30–3:30pm
15
✈ Ed arrives Syd
✈ Mikul arrives Syd
✈ Varun (TBC)
Meg PTO
16
Meg PTO
17
✈ Meg arrives Syd
18
Design System early review1 hr
19
Ryan PTO
Meg PTO
22
CMS Playback Overview1:30pm Syd · 2 hrs
23
Tech & Arch Review1pm Syd · 3 hrs
24
Content Mapping10am Syd / 4am Dub
25
Sitecore Demo1pm Syd / 7am Dub
26
CMS Wrap Up10am Syd / 4am Dub · 5 hrs
Discovery ends
29
30
M1 Discovery sign-off

Project is in discovery.

We are in week 2 of discovery. We completed the first official kick-off week, including formal onboarding, discovery kick-off, and key setup activities. This week is focused on immersion sessions, helping Horizontal build deeper context across TA's content, design, and technical landscape. View the Discovery Plan →

Current phase Discovery
Next major milestone Playback · 22 Jun
MED

In-person session attendance risk due to visas

Owner
Horizontal
Update
Mitigated — sessions re-sequenced and schedule adjusted. Current impact resolved.
Mitigated
FYI

Component count differences between Confluence and source code

Owner
Horizontal
Update
Early observation — documenting differences between Confluence spec and code source to share with TA. No action required at this stage.
Monitoring
On Track

Migration parity

Functional and quality equivalence with AEM across all 5 sites — features, integrations, assets, performance, SEO and accessibility maintained at go-live.

On Track

Operational improvements

Measurable efficiency gains for the TA team — faster content launch, easier personalisation, less duplicate effort, smoother day-to-day operations.

On Track

Future ready

Platform and team capability positioned to support TA's ambitions beyond day-one parity — new XMC features adopted, technical debt reduced.

On Track

On time delivery

All milestones tracking to plan for the Jan 2027 launch.

Current actions

Pre-kickoff 5 actions
Owner Action Deadline
TA + HD
Brooke and Meg to discuss office access for the team for next week and the week after Arrange access for HD team on-site at TA Sydney
This week
HD
Mikul and Nick to finish chatting about the URL mapping Follow up from technical immersion session
This week

Here is where you can find all the links to your project.

Here are all the deliverables for the project. Once a deliverable is added, the link will appear on the dashboard.

Build

UAT

Go Live

Hypercare

George Smith
Managing Director · Sponsor

George Smith

Your project sponsor — Managing Director and Horizontal leader, accountable for the success of the engagement.

Varun Shringarpure
Tech Lead

Varun Shringarpure

Your on-the-ground Tech Lead — close to the build, hands on with the team and the code.

Mikul Gohil
Frontend Tech Lead

Mikul Gohil

Our Frontend Tech Lead — responsible for the look and feel of the website.

Megan Lawler
Project Manager

Megan Lawler

Your Project Manager — responsible for the day-to-day running of the project.

Edward Stott
Strategist

Edward Stott

Your Strategist — shapes the vision and requirements that guide the project.

Sneha
Design Lead

Sneha

Your Design Lead — looking after the design system.

# Date Amount
(excl GST)
Amount
(incl GST)
Description Status
1 May 2026 $97,525.00 $107,277.50 Milestone 1 Contract Commencement & Discovery ✓ Paid
2 Jul 2026 $97,525.00 $107,277.50 Milestone 2 Foundational and Solution Design Pending
3 Sep 2026 $132,307.12 $145,537.83 Milestone 3 · Part 1 Development, Integration and Migration — checkpoint 1 Pending
4 Nov 2026 $132,307.12 $145,537.83 Milestone 3 · Part 2 Development, Integration and Migration — checkpoint 2 Pending
5 Jan 2027 $132,307.12 $145,537.83 Milestone 3 · Part 3 Development, Integration and Migration — completion Pending
6 Mar 2027 $58,195.27 $64,014.80 Milestone 4 Testing, Validation and Launch Pending
Source: Services Agreement & SOW. The agreed schedule above is the contractual reference point — for the signed copy, see the Contract folder on SharePoint. For payment status, raise queries with your Horizontal Project Manager.

Tourism Australia · AEM → Sitecore XM Cloud migration · 2 Jun – 30 Jun 2026

Note: Mon 8 Jun is a TA public holiday — no client sessions. Horizontal internal work continues remotely.

Team arrivals — in person at TA Sydney:

  • George — Mon 1 Jun (in person for all sessions throughout)
  • Ed & Mikul — Mon 15 Jun
  • Meg — Wed 17 Jun
  • Varun — weekend before Mon 15 Jun

Daily plan

Week of 1 Jun

Tue 2 JunWed 3 JunThu 4 JunFri 5 Jun
Major milestoneKickoff
Major deliverables
Kickoff deck
SessionsPre-kickoff prep (internal)
Kickoff (1 hr)
4–5pm Syd / 10–11am Dub
Tech onboarding
3–4pm Syd / 9–10am Dub
Business Overview Immersion (2 hrs)
3–5pm Syd / 9–11am Dub
Daily standup — agreed to start July
Weekly status
Horizontal tasks
Content: Kickoff prep
Design: Kickoff prep
Dev: Kickoff prep
Content: Kickoff
Design: Kickoff + DS Foundation start
Dev: Kickoff
Content: Pre-immersion prep
Design: DS Foundation
Dev: Tech onboarding, env setup
Content: Pre-immersion prep
Design: DS Foundation
Dev: Source-code audit
WhereRemoteRemoteRemoteRemote

Week of 8 Jun — Immersion week

Mon 8 JunTue 9 JunWed 10 JunThu 11 JunFri 12 Jun
Major milestoneTA Public HolidayImmersions complete
Major deliverablesTA Public Holiday
Content Audit delivered
Integration Specs delivered
SessionsTA Public Holiday
Content, DAM, Multilingual & Translation onboarding (pre-immersion)
3–4:30pm Syd / 9–10:30am Dub
Design Immersion (2 hrs)
1:30–3:30pm Syd / 7:30–9:30am Dub
Content Immersion (2 hrs)
3–5pm Syd / 9–11am Dub
Technical Immersion (2 hrs)
3–5pm Syd / 9–11am Dub
Daily standup — agreed to start JulyTA Public Holiday
Weekly statusTA Public Holiday
Horizontal tasks
Content: Pre-immersion prep
Design: DS Foundation
Dev: Source-code audit
Content: Content Audit drafting
Design: DS Foundation
Dev: Integration Specs drafting
Content: Content Audit
Design: DS Foundation
Dev: Integration Specs
Content: Content Audit
Design: DS Foundation
Dev: Integration Specs
Content: Content Audit DUE
Design: DS Foundation
Dev: Integration Specs DUE, SDD start
WhereTA Public HolidayRemoteRemoteRemoteRemote

Week of 15 Jun — Build week + early reviews

Mon 15 JunTue 16 JunWed 17 JunThu 18 JunFri 19 Jun
Major milestone
Major deliverables
Content Audit early review
Integration Specs early review
Design System early review
DS Foundation delivered
SessionsConsolidation (internal)Content Audit early review (1 hr)Integration Specs early review (1 hr)Design System early review (1 hr)
Daily standup — agreed to start July
Weekly status
Horizontal tasks
Content: Content Hub structure
Design: DS Foundation
Dev: SDD, Gap mapping, CMS prototype, Gap Analysis
Content: Content Audit early review + Content Hub
Design: DS Foundation
Dev: SDD, Gap mapping, CMS prototype, Gap Analysis
Content: Content Hub
Design: DS Foundation
Dev: Integration Specs early review + SDD, Gap mapping, CMS prototype, Gap Analysis
Content: Content Hub
Design: Design System early review
Dev: SDD, Gap mapping, CMS prototype, Gap Analysis
Content: Content Hub
Design: DS Foundation DUE
Dev: SDD, Gap mapping, CMS prototype final, Gap Analysis
WhereRemoteRemoteRemoteRemoteRemote

Week of 22 Jun — Playback week (in person)

Mon 22 JunTue 23 JunWed 24 JunThu 25 JunFri 26 Jun
Major milestonePlayback beginsPlayback complete
Major deliverables
Gap mapping playback
SDD playback
Content Hub Structure playback
Sessions
CMS Playback Overview (2 hrs)
1:30pm Syd · in person
Tech & Arch Review (3 hrs)
1pm Syd · in person
Content Mapping
10am Syd / 4am Dub · in person
Sitecore Demo
1pm Syd / 7am Dub · in person
CMS Wrap Up (5 hrs)
10am Syd / 4am Dub · in person
Daily standup — agreed to start July
Weekly status
Horizontal tasks
Content: Content Hub
Design: Playback prep
Dev: CMS prototype early review + SDD, Gap mapping, Gap Analysis
Content: Content Hub final
Design: Playback prep
Dev: SDD, Gap mapping final, Gap Analysis
Content: Playback support
Design: Playback support
Dev: Gap mapping playback + SDD, Gap Analysis
Content: Playback support
Design: Playback support
Dev: SDD playback + Gap Analysis
Content: Content Hub playback
Design: Playback support
Dev: Gap Analysis
WhereIn personIn personIn personIn personIn person

Week of 29 Jun — Sign-off

Mon 29 JunTue 30 Jun
Major milestoneDiscovery sign-off
Major deliverables
Gap Analysis & Go-Forward Plan sign-off
SessionsDiscovery sign-off
Daily standup — agreed to start July
Weekly status
Horizontal tasks
Content:
Design:
Dev:
Content:
Design:
Dev:
WhereRemoteRemote

Gantt — Full plan

Workstreams shown as bars. ◆ = major milestone. ▼ = major deliverable event. ✓ pink = weekly status. Grey column = TA public holiday. Daily standups begin July.

June 2026
WorkstreamTWTFMTWTFMTWTFMTWTFMT
234589101112151617181922232425262930
Major milestones
Major deliverables
SessionsPrepKOTOBICODICITIConsCArISrDSrCMrPpP1P2P3SOSO
Weekly status
Kickoff deck
Design System Foundation
Content & Asset Audit
Integration Specifications
Solution Design Document (SDD)
Component & Template Gap mapping
Sitecore CMS prototype
Content Hub Structure & Architecture Diagram
Gap Analysis & Go-Forward Plan
WhereRRRRRRRRRRRRRIPIPIPIPIPRR

Session legend

  • Prep  Pre-kickoff prep
  • KO  Kickoff
  • TO  Tech onboarding
  • BI  Business Overview Immersion
  • CO  Content, DAM, Multilingual & Translation onboarding (pre-immersion)
  • DI/CI/TI  Design / Content / Tech Immersions
  • Cons  Consolidation
  • CAr/ISr/DSr/CMr  Content Audit / Integration Specs / Design System / CMS prototype early reviews
  • Pp  Playback prep
  • P1/P2/P3  Playback Days
  • SO  Sign-off

Team on site at TA Sydney — June 2026

Green = confirmed.   Orange = confirming.

Person
234589101112151617181922232425262930
George — arrived Mon 1 Jun, in person throughout
Varun — weekend before Mon 15 Jun
Mikul — arrives Mon 15 Jun
Ed — arrives Mon 15 Jun
Meg — arrives Wed 17 Jun

All Discovery Sessions

All confirmed sessions across the Discovery phase. Remote sessions run in the 9–11am Dubai / 3–5pm Sydney window unless noted. IP = in person (Sydney, w/c 22 Jun).

# Date Session Sydney time Dubai time Length Attendees
1 Wed 3 Jun Kickoff 4:00–5:00pm 10:00–11:00am 1 hr TA + HZTL core teams across all departments
2 Thu 4 Jun Tech onboarding 3:00–4:00pm 9:00–10:00am 1 hr Dev team both sides
3 Fri 5 Jun Business Overview 3:00–4:00pm 9:00–10:00am 1 hr TA Business / Strategy / Executive
4 Tue 9 Jun Content, DAM, Multilingual & Translation onboarding 3:00–4:30pm 9:00–10:30am 1.5 hrs Brooke + content team, DAM/Library, Translation (GlobalLink owners)
5 Wed 10 Jun Technical Immersion 3:00–5:00pm 9:00–11:00am 2 hrs Nick + tech architects, Ben (QA), Infrastructure, Security, DevOps
6 Wed 10 Jun Transperfect call 1:30pm 7:30am 1 hr Translation / Transperfect team
7 Thu 11 Jun Content Immersion 3:00–5:00pm 9:00–11:00am 2 hrs Content, Authors, Translation, DAM/Library
8 Fri 12 Jun Design Immersion 1:30–3:30pm 7:30–9:30am 2 hrs TA brand + design team (Design, Brand, Visual, UX)
9 Thu 18 Jun Design System early review TBC TBC 1 hr Design leads both sides
10 Mon 22 Jun CMS Playback Overview IP 1:30pm 7:30am 2 hrs TA + HZTL core teams
11 Tue 23 Jun Tech & Arch Review IP 1:00pm 7:00am 3 hrs Tech architects, Nick + HZTL tech leads
12 Wed 24 Jun Content Mapping IP 10:00am 4:00am 3 hrs Brooke + content team, HZTL content team
13 Thu 25 Jun Sitecore Demo IP 1:00pm 7:00am 2 hrs TA + HZTL full team
14 Fri 26 Jun CMS Wrap Up IP 10:00am 4:00am 5 hrs TA + HZTL full team